Article by Stanley D. Berger

Fogler, Rubinoff LLP

A recent decision from the Yukon Territorial Court is a reminder of how important communication between the regulator and the regulated can be. At the same time, perhaps as an illustration of the power of fate, at least in a narrow set of circumstances, communication may make no difference at all. In R. v. Cobalt Construction Inc., released September 14, 2017 the sole shareholder/director and his road construction company were charged with failing to provide a detailed decommissioning plan in accordance with the conditions of a permit for a facility designed to accept, store and treat dirt contaminated with petroleum hydrocarbons. The defendants failed to establish a due diligence defence to the charges because of poor communication with the authorities, but were acquitted anyways because it was impossible for them to comply given the weather conditions during the time frame for compliance.

Cobalt Construction Inc. Vehicles (Credit: Brian Boyle/CBC)

The regulator’s plan required sampling results be obtained after contaminated piles of dirt were tilled as configured. The soil was to be mixed two weeks before the samples were taken for analysis. The sample results would then inform further elements of the plan including identification of an appropriate receiving facility. The defendant director testified that it would have been impossible to till the soil as required within the time frame set out by the regulator because snow on the ground would have prevented use of the excavator and the ground would have been frozen requiring a ripper to be used to break up the ground, thereby destroying the configuration of the piles. The defendants had in the initial plan set out dates for sampling beyond the time frame required by the regulator, but failed to offer any explanation as to why the sampling could not be done within the imposed time frame. Further, the defendants at no time sought an extension of time for performing the sampling. The Crown prosecutor argued that the authorities were under no obligation to notify the defendants that their initial plan was insufficient to satisfy the regulatory requirements. The Court observed that the more detailed the decommissioning plan provided, the more likely fairness would demand notification by the authorities of the deficiency and an opportunity to correct it. Conversely, the less detailed the plan, the less likely fairness would demand notification. “To decide otherwise would mean that a defendant could evade responsibility and delay consequences simply by making a cursory attempt at compliance.” The Court suggested that if the defendants had fleshed out the plan and included options for receiving facilities and restoration that would be contingent on the sampling results, this would trigger notification by the regulator that the plan was deficient. However, the initial plan provided was so clearly and objectively deficient on its face that the regulator had no obligation to notify the defendants that the plan did not comply and did not further require the authorities to give the defendants an opportunity to rectify the deficiencies prior to laying charges. The Court consequently rejected the defence of due diligence. Nevertheless, the Court acquitted the defendants, accepting the defence of impossibility, notwithstanding the absence of due diligence.

 The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

________________

About the Author

 Stanley Berger is certified by the Law Society of Upper Canada as a specialist in environmental law.  He was called to the Ontario Bar in 1981. He joined the law firm of Fogler Rubinoff on July 4 2013.  Stanley was the founder of the Canadian Nuclear Law Organization and served as its President between 2008-2015, and remains a board member.  He is also is a former President of the International Nuclear Law Association.  He has taught nuclear law for the Nuclear Energy Agency in France and is an adjunct professor for York University’s Professional Master’s Degree in Energy.  Stanley is the author of a quarterly publication entitled “The Prosecution and Defence of Environmental Offences” and edits an annual review of environmental law.

Stanley represents suppliers and operators in the nuclear industry on nuclear liability, regulatory and supply chain issues. He provides legal advice to the Nuclear Waste Management Organization. Other clients include the CANDU Owners Group and a large Ontario municipality. His environmental practice includes litigation before courts, boards and tribunals, as well as solicitor’s work on behalf of renewable energy companies, landowners and waste management entities. He represented a First Nation on regulatory matters relating to a renewable energy project. His practice also includes the protection of proprietary information on applications before Ontario’s Freedom of Information and Privacy Commission.

This article was originally published on the Fogler, Rubinoff LLP website.